With few of us zooming-in yesterday, we continued the process of putting all our ideas together. Over the weekend, all three teams have been working on different conceptual design models with an orientation [...]
Zoooming In


DESIGN+BUILD PROJECTS BY CLEMSON COMMUNITY BUILD

With few of us zooming-in yesterday, we continued the process of putting all our ideas together. Over the weekend, all three teams have been working on different conceptual design models with an orientation [...]

Today, as an initiative to give the students of Edith L. Frierson Elementary the exposure to architecture and design, we drove out to Frierson Elementary and helped the 4th and 5th grade kids to build a structure. The students quickly became familiar with the system, and built this amazing small little room. They split up [...]

Another day another truss. Now that we have moved on to the "real deal" of truss fabrication, and everyone is up to speed on the actual process of building our amazing trusses, let's talk a little bit about the mental preparation it takes to be a successful truss assembler, but most importantly, a Studio V [...]

Over the weekend a few of our Studio V members where working in the shop to construct a mock up of our truss system. Mock Up 1: We began with a half-sized scale truss and went through all the steps it would take to fully construct our sandwiching of layers and members. Throughout this time [...]

Today is a big day. Today is the day the final major elements get completed. This week has been critical, as people have been working hard to get all elements left prepped and in place. Originally, Thursday the 25th was set to be the "shovels down" day. Unfortunately, that did not happen. As we have [...]

"CONCRETE'S HERE!" - Dave Pastre After a long weekend of adjusting the formwork and pumping water again, and again, and maybe again from the rain the site was officially prepped. While all that was going on groups were in the shop working hard to put together the formwork for the "clutter in the gutter" (storage, [...]
What a week it’s been. The Corrine Jones CD set was officially sent to the structural engineer yesterday, Thursday March 14. I thought that day would never come. Round after round of red lines, a back and forth about construction and methods, and quite a few nights of minimal sleep. But the set is drafted [...]

If you’ve been keeping up with us the last couple of days, you know that yesterday we presented our overall design for Corrine Jones Park Pavilion. After presenting, as you may know from Aaron's spot on post, we had a debrief of what was discussed with everyone there. We began to work through some of [...]

As stated in the previous blog post we have decided on a kite-like shape for the roof of the shaded structure. In addition, we have been working on different variations of how we can arrange the post and beams that would support the roof. Since the shape of the roof is not a typical square [...]