This week we started on our design process for Singleton Park's garden! We were all excited to get into the weeds of it, and we had our first meetings with Prof. Pastre today on our work so far. We all were randomly assigned different "Site Approaches" which delineated generally where the main gathering space and [...]

A Handy Tool

There have been many tasks involved with the Mural Wall Project. Yesterday, I learned about the process of planning the mounting location of the Mural Board onto the wall itself. For this process, we used a Gyroscopic, 360 degree Lazer level. The first time we were introduced to this tool was on the Frierson site [...]

The Great Meet!

It is so exciting when you get to meet with people who have actually made the project possible, isn't it? The discussion started with the introduction of the visitors. Jesse Blom, the Executive Director at The Green Heart Project; Interim Executive Director, Leslie Wade from Charleston Parks Conservancy; Courtney Olson, Urban Agriculture Manager; Jason Kronsberg director [...]

Question Everything?

Today is the day we meet with all of the stakeholders for our newest project located at Eric Cornelius Singleton II Park! Our project is aimed to be a student garden for Meeting St. Academy which is located adjacent to our site. On Wednesday, we were lucky enough to be joined by Barry Yoakum who [...]

Making a Game Plan

While taking a tour all over Charleston to visit past projects, we were able to experience each project within their distinct context. It was very inspiring to see how each build settles into the space and it was difficult to imagine the space without the build. Each project existed as if it was meant to [...]

Perusing the Portfolio

On Friday, we spent the day visiting the various sites of some of the past and on-going A+CB projects.  This was a great opportunity for us to reflect on the history of the program, to appreciate the hard work of many of the previous A+CB students, and to recognize the level of quality in the [...]

The Journey Begins!

The first day of class at CACC was unlike I had ever experienced in school. There was no conventional presentation or theoretical lesson. Instead, there was a very interesting workshop for laser cutting. It was fun learning the new skill which will be very helpful not only in our academics but in professional life as [...]

Stable Gables

This week is a big week for our crew as we've been split in two since this past weekend. One crew has been on site assembling the diagonal steel membranes on the trellis and beginning to raise the gable pieces of the large slab structure, while another crew has been in the shop meticulously assembling [...]

Pour Galore

On Wednesday, our second round of concrete pours was completed. We reached site at around 9:00 AM and made one last walk-around of our form work and rebar in preparation for a 10:30 pour. This included tightening the bolts at the pencil rods of our trellis formwork and oiling the formwork at the large slab [...]

Meet The Team

While part of the group is out on site today completing our final concrete pour, I'd like to take the time to introduce our team! There are some old faces that you've seen in last semester's blog posts, and some new faces that have joined us for this semester. Although it's been a little rough [...]