Surveying The Site

After meeting with city of Charleston representatives, we split ourselves into groups on Friday to divide a handful of tasks amongst ourselves. Some of our classmates studied the history of Steven Washington Park, others studied the community demographics, and others focused on precedent studies. Myself and two others tasked ourselves with measuring everything on the [...]

Put a Roof On It

As of yesterday, all of our purlins have been attached onto our structure, and now we wait for the cedar shake shingles to arrive! As a crew continued to work on setting the purlins, Anna and I headed over to Old Towne Creek with David to work some finishing touches with stain on the donor [...]

Fabrication Almost Done!

Today, the studio made major progress. We’ve officially finished up most of the remaining shop work! The columns, truss, cross bracing, and rafters are all complete, and over half of the purlins have been sanded and stained. We even loaded up the first truckload of pieces to head to the site. All left to do [...]

Half-Scaled Models

Over the weekend, the class split into two separate crews. A handful of students finished building the wall at Old Towne Creek, while others began to work on cut-sheets for the pavilion being constructed at Plymouth Park. Those cut sheets were used today to create half-scaled portions of our pavilion's roof truss system. This involved [...]

Enjoying the Charleston Sun

The studio prioritized time outdoors this weekend... at the worksite! Working Friday afternoon and all day Saturday, our team spent many hours on site this weekend building the Old Towne Creek Donor Wall. On Sunday, some students went back to the site to finish the rafters and purlins while three of us went to the [...]

Researching Charleston

This week is an exciting one for the Community Build Studio! Today we are meeting with the structural engineer to work on the truss system in our design, and iron out some structural details. Some of the students in the class have started on construction documents and a larger scale connection model of the pavilion [...]

A Fast Start To February

In the Community Build studio, the beginning of February has been eventful. We are currently moving towards a February 18th deadline as we work to synthesize our many ideas and narrow down our final group design to be proposed to the city. Most of the studio met yesterday to compare sketches and study models, then [...]

Mood Board Mapping

  This week in studio has been all about dissecting our small group designs in order to come up with a new collective design for the Plymouth Park structure. After taking on individual sketching earlier in the week, the class came together to pin up our sketches and create a mood board with images that [...]

Letting the Past Influence the Present

Good morning and happy Martin Luther King Day! Dating back to the fall of 2010, Clemson University has had a profound impact on the landscape of Charleston as we know it today. 30 semesters of Design + Build studios at the Clemson Architecture Center Charleston (CACC) have yielded dozens of structures across the city. Every [...]