We had quite the eventful weekend in the shop. Let’s recap!
FRIDAY:
Our shipment of wood came in, so we brought it inside like ants. We #elevated it onto some excellently laid-out wood boards, thanks to Tyler. One team went straight to cutting and milling the wood, while the rest of us wire-brushed all of the rust off the ends of the steel rod and steel wire mesh that we had received on Thursday. Thursday also marked our first bloodshed in the shop. RIP Ethan’s finger (he’s fine btw).
After about three straight hours of removing rust and absolutely mangling the brushes (oops), we ended up looking like we had come straight out of the mines. Feeling extra rusty and dusty. We recently found a pack of dust masks, which was definitely needed, though I’m sure we were all blowing out grey snot for the next few days. Of course, just as we finished this up, David arrived back at the studio with a pack of steel that we needed to get inside.
We learned a lot about the importance of communication over the next 10–15 minutes. When it came to relocating heavy steel that required three people to lift at a time, communication was key to making sure no one got a finger pinched while placing the stacks. We made sure the person at the front lined up the end of the steel with the stack below, then we followed their lead by lowering it straight down, with the person on the opposite end dropping first, followed by the middle, and finally the front. I also personally learned that I need to work on my form when lifting the middle, since that is where most of the weight is concentrated. It is very easy to pull something in your back if you aren’t careful!
After all that was done, we discussed how we would set up shifts for the remainder of the weekend to get a good start on cutting and milling the wood, as well as working with the steel to begin fabricating the trellis.
SATURDAY:
The day of the whole flooding debacle (big word).
The morning shift had quite the surprise walking into work. The AC unit had become a unique new feature for the shop – a waterfall! Luckily, we had elevated the wood Friday night. After getting buckets set up and powering on all the fans to help dry the floor, we got back to work.
We continued cutting and milling the wood, along with some steel cutting. Using the steel cutter (infamously known as the goo machine) requires a lot more thought than you might anticipate, especially when cutting steel angle to create mitered edges. Paying attention to which side of the flange is facing up, as well as which direction the 45 degree cut is set, can make or break your cut.
We also learned that being specific when identifying different members is important. If you are trying to differentiate between a 7′-8″ piece and an 8′-2″ piece, simply calling them the 7 footer or 8 footer could potentially result in cutting a piece too short. The same idea applies when marking holes. We had to make sure we laid out the pieces correctly so that the holes were marked on the correct side of the angle and would line up properly with the posts later on when the pipe is welded on. These were small details, but they required a lot of attention to make sure everything would fit together correctly.
SUNDAY:
At approximately 8am, I’m not sure why they wanted to go in so early, a new crew went into the shop to get all of the freshly milled and cut wood primed and ready to get painted.
But first we have to decide on a color…
A good portion of us met with David later in the day to look at potential color options for the pavilion and narrowed it down to NOT using a color. Keeping natural tones throughout the structure will help it blend into the conservancy’s property without distracting from the natural landscape with a harsh or overly bold color. We also discussed how the top portion of the trellis may not be able to be curved as we had originally designed. Since our bender (yes, that’s actually what it’s called) can only accommodate material up to about 1.5″ wide, while our steel is 3″ wide, we will have to look into other resources or fabrication methods for creating the curved portions.
The night crew went down after our quick meeting and finished up the wood since it had dried from the morning’s work. Hopefully we’ll be able to get this wood wall mock-up finished sometime this week and also begin welding the trellis walls.
Stay tuned!