Site Plan Iterations + Snow

Post first meeting with the council from Dolphin Architects, the Sea Islands Conservancy and the Gullah Geechee Chamber of Commerce representative Cory, we started site plan iterations for where the best locations for our stands would be. Some considerations driving these plans being visibility from the street/entrance, incorporation into nature and accessibility. With 3-5 iterations per [...]

Trust the Process

With spring cleaning complete and the initial site visit for this semester's sweetgrass stand project concluded, students now pivot to compiling project information, research, and precedent studies for their upcoming presentation on Wednesday. Both the architecture students and historic preservation students are currently collaborating to make this happen. All hands on deck! While everybody is [...]

Final Review!

The studio held our final review for the semester today, gathering faculty, staff, students, and community members under our pavilion. Even though the structure isn’t fully complete, it was exciting to share the project and see the enthusiasm the community and city had for it. The review felt less like a critique and more like [...]

Preparing For The Grand Opening!

For the past little while the class has been on site, rushing to get everything built for Wednesday. Over the weekend, all the furniture was welded, grinded, and painted. Additionally, the central columns were placed, and the central beams were installed. Today, we put up the outer columns, which was followed by the outer beams [...]

Back to Build Mode

After coming back from Thanksgiving break, our studio is focused on finishing up our build work in the shop so that we can start assembling on site. Right now, we're working to finish the columns; we've cut them, drilled the holes for bolts, cut a slot for knife plate connections, and have put on our [...]

Pour Prep

This week in studio, we've been preparing for our first concrete pour which will be for our pavilion's slab. We've spent the weekend and the early parts of. this week prepping our site by digging out the area that the slab will be in, and then laying out the rebar. We've also had a crew [...]

Movin’ & Groovin’

Today the studio split into two crews. My group went to the site to measure out where the pavilion would be. This involved four of us stretching tapes out and re-adjusting everything so it makes a perfect square and sits well between the trees. We had to hammer rebar into the dirt to mark spots [...]

CD Set Markups

Today in studio we received some feedback from our structural engineer, John Moore, on the CD set we had sent to him for his approval. John sent us back some of our sheets with his own markups, indicating elements that needed to change or be adjusted. A lot of the comments that were discussed today [...]

Shop Drawings

This past weekend, most of the class put in a handful of hours in the studio to keep things on schedule. Some studio members have been working on perfecting the revit model and fixing small issues and errors that we have come across. Others have been correcting the rebar and making adjustments to the concrete [...]

Block Party Build

This week in ITC, groups are starting to build their designs for the Metanoia Block Party this weekend. All of the projects that are being built are constructed out of cardboard. My group has come up with a design for seating that is inspired by the craft of traditional Gullah Geechee quilting. Our design includes [...]