Looking to Friday!

Coming off of our "heavy" snow weekend, we are continuing to produce individual schematic iterations of sweetgrass basket stands. Drawing on feedback from our meeting with Dolphin Architects, the Sea Island Conservancy, and our artisan representative, Corey, our team has divided our areas of focus into three categories. The first being a layout of stands [...]

Donuts and Adobe

Starting the afternoon with Duck Donuts (shout out Malu and her firm Coast Architects) and a short standup, we all started work on getting the finishing touches of our research and precedent presentation together. Site analysis, local history, and precedent studies are all deep in research for a comprehensive display to the Conservancy of the [...]

Trust the Process

With spring cleaning complete and the initial site visit for this semester's sweetgrass stand project concluded, students now pivot to compiling project information, research, and precedent studies for their upcoming presentation on Wednesday. Both the architecture students and historic preservation students are currently collaborating to make this happen. All hands on deck! While everybody is [...]

Finishing Cleaning!

With the Spring Cleaning phase coming to an end, only a handful of projects remain to be finished. The tallest task among the remaining cleanups includes the project at Stephen Washington Park. The crew responsible for this project must finish their design solution to comply with ADA codes. At this pavilion, there are a couple [...]

Preparing For The Grand Opening!

For the past little while the class has been on site, rushing to get everything built for Wednesday. Over the weekend, all the furniture was welded, grinded, and painted. Additionally, the central columns were placed, and the central beams were installed. Today, we put up the outer columns, which was followed by the outer beams [...]

A Busy Week!

This week has been eventful! As Anna discussed, we poured our concrete slab this week. The process was fascinating, and really fun to be part of! Back in the shop, a group of us finished building the formwork for our concrete piers. After we remove the formwork from the slab, we will install this formwork [...]

Breaking Ground!

We officially broke ground on site! With the concrete formwork nearly complete and rebar on its way, the next week will be dedicated to bending rebar and preparing the site for the slab pour and concrete footers. The images show us digging out the footers for the structural spine of the project and digging to [...]

Movin’ & Groovin’

Today the studio split into two crews. My group went to the site to measure out where the pavilion would be. This involved four of us stretching tapes out and re-adjusting everything so it makes a perfect square and sits well between the trees. We had to hammer rebar into the dirt to mark spots [...]

Last Day Before The Metanoia Block Party

Tomorrow is the Reynolds Avenue Homecoming event for our Intro to Craft class. The groups have been working hard this week to produce cardboard installations, graphics, and signage for this event. My group has been working on an installation that draws from the ropemaking traditions of historic Charleston, and the sensory experience of light, to [...]