Site Plan Iterations + Snow

Post first meeting with the council from Dolphin Architects, the Sea Islands Conservancy and the Gullah Geechee Chamber of Commerce representative Cory, we started site plan iterations for where the best locations for our stands would be. Some considerations driving these plans being visibility from the street/entrance, incorporation into nature and accessibility. With 3-5 iterations per [...]

Design Time!

Today was an eventful day! After a productive meeting with the studio consultants, we began working on individual design, preparing for studio on Friday. In these first iterations, we are focusing on site options and massing potentials . Image: Printed scaled site plans to sketch onto After classes today, MaKayla shared our initial research and [...]

Donuts and Adobe

Starting the afternoon with Duck Donuts (shout out Malu and her firm Coast Architects) and a short standup, we all started work on getting the finishing touches of our research and precedent presentation together. Site analysis, local history, and precedent studies are all deep in research for a comprehensive display to the Conservancy of the [...]

Trust the Process

With spring cleaning complete and the initial site visit for this semester's sweetgrass stand project concluded, students now pivot to compiling project information, research, and precedent studies for their upcoming presentation on Wednesday. Both the architecture students and historic preservation students are currently collaborating to make this happen. All hands on deck! While everybody is [...]

Finishing Cleaning!

With the Spring Cleaning phase coming to an end, only a handful of projects remain to be finished. The tallest task among the remaining cleanups includes the project at Stephen Washington Park. The crew responsible for this project must finish their design solution to comply with ADA codes. At this pavilion, there are a couple [...]

Final Review!

The studio held our final review for the semester today, gathering faculty, staff, students, and community members under our pavilion. Even though the structure isn’t fully complete, it was exciting to share the project and see the enthusiasm the community and city had for it. The review felt less like a critique and more like [...]

A Busy Week!

This week has been eventful! As Anna discussed, we poured our concrete slab this week. The process was fascinating, and really fun to be part of! Back in the shop, a group of us finished building the formwork for our concrete piers. After we remove the formwork from the slab, we will install this formwork [...]

Breaking Ground!

We officially broke ground on site! With the concrete formwork nearly complete and rebar on its way, the next week will be dedicated to bending rebar and preparing the site for the slab pour and concrete footers. The images show us digging out the footers for the structural spine of the project and digging to [...]

Movin’ & Groovin’

Today the studio split into two crews. My group went to the site to measure out where the pavilion would be. This involved four of us stretching tapes out and re-adjusting everything so it makes a perfect square and sits well between the trees. We had to hammer rebar into the dirt to mark spots [...]