Friday we finally were able to break ground! Lot’s of it.
Everyone was in high spirits to be out of the wood shop and finally on site we were able to auger and dig out all of the holes for the footings.
The process went like this:
The location of the 2’x2′ squares were already marked with flags and spray paint previously. A couple of students familiarized themselves with how to use the auger and loosened the dirt in the 3′ deep holes for the rest of us to shovel the dirt out behind them. It was a team effort to shovel the dirt out, move the dirt to a big pile and ensure we were keeping all of the dimensions accurate. After the holes were dug, a few students went behind and filled the bottom with a layer of gravel.
After hours of working away, and one short Jersey Mike’s break, we dug out all 28 or so foundation holes and were able to return the auger early and save our weekend from having to return to site.
Of course, we had to end the day by a nice relaxing break in the holes…
Next week is a short week with Thanksgiving ahead, but we are hoping to get out to site on Tuesday to get the posts set in place!