“I trust Dave, in the shop” – Stevie Chen

So it’s Friday, seven more days till our projected completion date of the 14th, and everything is falling into place. Yesterday we started spray painting and priming the door hinges, and have them out to dry. We also are making large strides in the completion of the roof. IMG_2270

This is BIG news because we had hit some hiccups relating to the angle at the top. Today we are planning on making jigs for it, so we can economize the process of construction.

We are also planning on assembling the slats into the door frames as well as finish painting the trusses. Like I said everything is falling into place.