Covering up with Purlins and Rafters

Great progress has been made on the site with the installation of all the rafters and almost all of the purlins. The rafter installation process went relatively smooth with only a few cross-brace systems needing to be shaved down due to having too tight of a fit. Other than those slight adjustments here and there, the rafter systems all were installed prior to noon and after a lunch break we began the purlin installation. For the purlins we were able to complete the installation on the steeper slope and about a quarter of the other side. Once we got a system down, the process exponentially speed up and I am sure we can knock the rest of them out tomorrow!

Prep for the purlins
Installing purlins