Working Hard or Hardly Working

Hello all,

We have been up to a few things.

1. Finilizing CD set.

We are adjusting a final package of CD sets to be approved by all partnering individuals and organizations. The roof is changing from cedar shake to a standing seam aluminum to fit the language of past projects and the parks vernacular.

This changes Purlin Layout, expenses, and roof load, which have budget and engineering implications.

2. Laying out piers (Guides)

Marking out the pier placements over water is a challenge. The final measurements system included string line and a floating outline Frame on the surface of the water, held in place by stakes.

3.Budgeting

We have been calculating and recalculating budgets with the updated design, reaching out to vendors and seeking donations. Price increases due to COVID disrupting supply chain have not been friendly to us.

 